Luton Borough Council
Plan timetable
About this data
We accept data in different formats and standardise it, so that we can combine it with data from other sources. This means the data we show might be in a different format to the data you provided. For example, we standardise all dates as YYYY-MM-DD.
| Reference | Plan | Plan event | Event date | Actual date | Entry date | Notes |
|---|---|---|---|---|---|---|
| LBC_Notice_Commence | luton-borough-council-local-plan-2050 | publish-notice-intention-commence | 2026-05-28 | 2026-05-28 | 2026-05-28 | |
| LBC_Notice_Scoping Start | luton-borough-council-local-plan-2050 | scoping-consultation-start | 2026-05-28 | 2026-05-28 | 2026-05-28 | |
| LBC_Notice_Scoping End | luton-borough-council-local-plan-2050 | scoping-consultation-end | 2026-07-23 | 2026-05-28 | ||
| LBC_Sites Start | luton-borough-council-local-plan-2050 | sites-consultation-start | 2026-05-28 | 2026-05-28 | 2026-05-28 | |
| LBC_Sites End | luton-borough-council-local-plan-2050 | sites-consultation-end | 2026-07-23 | 2026-05-28 | ||
| LBC_Gateway 1 Assessment | luton-borough-council-local-plan-2050 | gateway-1-self-assessment | 2026-10-22 | 2026-05-28 | ||
| LBC_Notice_Plan Start | luton-borough-council-local-plan-2050 | plan-content-evidence-consultation-start | 2027-05-13 | 2026-05-28 | ||
| LBC_Notice_Plan End | luton-borough-council-local-plan-2050 | plan-content-evidence-consultation-end | 2027-06-24 | 2026-05-28 | ||
| LBC_Gateway 2 Sought | luton-borough-council-local-plan-2050 | gateway-2-advice-sought | 2026-08-17 | 2026-05-28 | ||
| LBC_Gateway 2 Published | luton-borough-council-local-plan-2050 | gateway-2-advice-published | 2026-05-28 | TBC | ||
| LBC_Notice_Proposed Start | luton-borough-council-local-plan-2050 | proposed-plan-consultation-start | 2027-11-18 | 2026-05-28 | ||
| LBC_Notice_Proposed End | luton-borough-council-local-plan-2050 | proposed-plan-consultation-end | 2028-01-20 | 2026-05-28 | ||
| LBC_Gateway 3 Sought | luton-borough-council-local-plan-2050 | gateway-3-advice-sought | 2028-02-17 | 2026-05-28 | ||
| LBC_Gateway 3 Published | luton-borough-council-local-plan-2050 | gateway-3-advice-published | 2026-05-28 | TBC | ||
| LBC_Gateway Further Advice Sought | luton-borough-council-local-plan-2050 | gateway-3-further-advice-sought | 2026-05-28 | TBC | ||
| LBC_Gateway Further Advice Published | luton-borough-council-local-plan-2050 | gateway-3-repeat-advice-published | 2026-05-28 | TBC | ||
| LBC_Notice_Examination Submitted | luton-borough-council-local-plan-2050 | examination-submitted | 2028-06-15 | 2026-05-28 | Submission of the Local Plan to the Secretary for State for examination. | |
| LBC_Notice_Examination Published | luton-borough-council-local-plan-2050 | examination-recommendations-published | 2026-05-28 | A public examination of the local plan against the tests of soundness, set out in national policy. Estimated June to October 2028 | ||
| LBC_Notice_Main Start | luton-borough-council-local-plan-2050 | main-modification-consultation-start | 2026-05-28 | TBC | ||
| LBC_Notice_Main End | luton-borough-council-local-plan-2050 | main-modification-consultation-end | 2026-05-28 | TBC | ||
| LBC_Notice_Examination Start | luton-borough-council-local-plan-2050 | examination-pause-start | 2026-05-28 | TBC | ||
| LBC_Notice_Examination End | luton-borough-council-local-plan-2050 | examination-pause-end | 2026-05-28 | TBC | ||
| LBC_Notice_Adopted Adopted | luton-borough-council-local-plan-2050 | adopted | 2028-12-22 | 2026-05-28 | ||
| LBC_Notice_Additional Start | luton-borough-council-local-plan-2050 | additional-consultation-start | 2026-05-28 | TBC | ||
| LBC_Notice_Additional End | luton-borough-council-local-plan-2050 | additional-consultation-end | 2026-05-28 | TBC |